Which method is used in agile to track progress during a sprint?

Prepare for the CBAP v3 BA Exam with our interactive quizzes. Utilize flashcards and multiple-choice questions designed with explanations to help you succeed. Get exam-ready with our focused study resources!

In agile methodologies, the burn-down chart is a key tool used to track progress during a sprint. It visually represents the amount of work remaining in a sprint over time, typically displayed in a graph format. This chart helps the team monitor their progress against the sprint goals by showing how much work has been completed versus how much work is left to complete.

The burn-down chart is particularly valuable because it allows the team to quickly see if they are on track to complete their tasks by the end of the sprint. If the line indicating progress isn't declining as expected, the team can take corrective actions early to adapt their plans. This contributes to a more flexible and responsive approach to project management, which is a core principle of agile.

Other methods such as progress charts, task lists, and milestone trackers may provide valuable information but do not encapsulate the specific focus on work remaining and the duration of the sprint as effectively as the burn-down chart does. The burn-down chart’s focus on remaining work within the timeline of the sprint is what makes it an essential method for tracking progress in agile environments.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy